Governor Spencer Cox says nuclear, geothermal, and solar power should help fuel the colossal Stratos Project.

  • tburkhol@slrpnk.net
    link
    fedilink
    arrow-up
    1
    ·
    4 天前

    As near as I can tell, the proposed data center is 40,000 acres and 9 GW. 9 GW continuous supply would need something like 90 GW peak solar panels and maybe 650 GWh of batteries (3 days, for nights & storms). That’s another 300,000 acres just for the panels.

    Not saying it can’t be done, but you have to find a lot more land. If you’re just trying to scam investors, it’s way easier to wave your hand and say ‘gas pipeline’ than to invite criticism of a massive solar project in addition to the massive data center project.